Already validated or listed PoAs need to complete validation and submit the request for registration by 24 October 2020 if they do not wish to apply the new renewable energy eligibility rules. The PoA boundary defined and technology types included at the time of listing must remain unchanged during validation. At the time of the next renewal of the PoA, the inclusion criteria for new Voluntary Project Activities (VPAs)/Component Project Activities (CPAs) will be updated in line with the new eligibility rules as defined in Renewable Energy (RE) Activity Requirements, paragraph 2.1.3

 

PoAs submitted for registration after 24 October 2020 will define the VPAs/CPAs inclusion criteria in line with the new RE Activity Requirements, paragraph 2.1.3.