No. The requirement to have different audit teams does not apply to combined Design Certification with first verification and performance review for a given project (paragraph 5.1.53, Principles and Requirements V1.2, p 28). The same audit team may perform both validation and verification for combined Design Certification and first performance certification for a given project.
The project has a combined Design Certification of first verification and performance review. Does the Validation and Verification Body have to supply two different audit teams? Print
Created by: Deepak KumarSC
Modified on: Wed, 29 Apr, 2020 at 12:47 PM
Did you find it helpful? Yes No
Send feedbackSorry we couldn't be helpful. Help us improve this article with your feedback.