The documents to be submitted during PoA design change shall be in line with the list of documentation mentioned in Annex A of the Principles & Requirements but with relevant documents to be submitted at the PoA level. 

 

PoA-level design change request does not require the Voluntary Project Activities (VPAs)/ Component Project Activities (CPA)-level documents to be submitted for design change review upfront. For the PoA-level design change request, the Coordinating/Managing Entity can only submit PoA-related documents such as the PoA-Design Document.